C-65.1, r. 5 - Regulation respecting construction contracts of public bodies

Full text
34. Where it is decided after tenders are opened that a contract is not to be awarded following a public call for tenders or, if a quality evaluation is to be made, after a meeting of the selection committee, the tenderer that would have been awarded the contract receives as compensation and final settlement for expenses incurred the amount of
(1)  $2,000, if the tender is equal to or greater than $500,000 but less than $1,000,000; or
(2)  $5,000, if the tender is equal to or greater than $1,000,000.
O.C. 532-2008, s. 34.